Monday, May 2, 2016

Reliability Begins with Effective Job Plans: A guest post from Coach Allen Canaday

Are you still using a job plan that doesn’t contain performance standards for proper work execution?  You know, performance standards, the technical information the job plan conveys to the technicians performing the task. This is the specific knowledge required in order to ensure the step is completed without introducing an error or failure.  I’m talking about such “trivial” information as torque specifications, belt tension, alignment tolerances and pressure settings to name a few.  Oh, you don’t need it?  You have a very experienced and talented work force who is overflowing with tribal knowledge? Why spend the time and money to research the correct performance standards?  After all, I don’t want to insult my technicians by implying their knowledge and skills are no longer adequate.  We’ve done it this way for years.
OK, so you don’t have performance standards in your job plans and don’t really see the value of taking the time to research and document them in the job plans.  Your current technicians understand what is required when they read statements such as “replace as necessary”, “adjust as needed” or “inspect for normal wear”.  You’re in great shape as long as most of them remain healthy, content, well-paid or never retire.  Have you considered these possibilities?  Oh, don’t forget about the new state-of-the-art manufacturing facility opening across town next year.  A new facility, modern equipment in an ultra-clean environment with salary ranges far beyond anything your facility can counter-offer.  Are you still confident with your tribal knowledge database?
The status quo will change, bet on it!  “Build it and they will come” was the famous quote from Field of Dreams.  There is tremendous competition in today’s marketplace for skilled technicians.  When the new facilities are built, and they will be, they will recruit the best of the best.  Some of those best will be yours!  The color of loyalty today is “green”.  If you are unable to compete in the salary and benefit arena, you will lose tribal knowledge!  How will you prepare for the “loss of knowledge” while there is still time?  In many cases this loss of tribal knowledge can be compared to your CMMS crashing and there is no back-up data. 
Invest in your job plan library without delay!  Why?  Because it’s the right thing to do.  Accurate job plans not only help capture tribal knowledge, but will force you to research many facets of your asset base that haven’t been explored.  The development of good job plans require research utilizing OEM documents and the inclusion of tried and true methods your technicians have developed over the years.  Other benefits of updating job plans include time estimate accuracy for each step of the plan, proper sequencing of the tasks, updating warnings and cautions as safety procedures may have changed and a review of the BOM’s. 
Your workforce’s skills and experience are dynamic.  As experienced employees leave they are generally replaced with less experienced employees, certainly less experienced in your facility.  Keep this fact in mind as job plans are reviewed and developed, the job plans have to be written to the level of understanding, training and skills of your workforce.  As the number of more senior employees leave the company the level of detail in the job plans may certainly have to increase to ensure continued or even improved performance can be attained.  Are you sure you can’t make a plan to update your job plans?

Monday, December 16, 2013

Do You Need More Wedding Planning in Your Plant Outage?

So lets talk about really solid outage planning and scheduling. Not the half-hearten effort that I sometimes see organizations pass off as planning and scheduling, we want to see the good stuff.
Imagine if you will, a wedding. It could be yours or your kids, but think back to that process. Here are just some of the key pieces that were crucial to creating that special day.
Scheduling starts early with all big life turnarounds:
You picked a date for execution of the plan. Hopefully, it was not a reaction to a problem that was brought to your attention during the previous week and instead was scheduled well in advance (a year) and with the full agreement of all parties. It hopefully was picked based on resource availability and with the agreement of both members of the operations team, the bride and groom.
Budget bound:
A high level budget was created based on either what you were willing to spend, what you had available, or what you had been allocated from the parental organization. This at first is an order of magnitude or a not to exceed number that you broke down and further detailed as the planning process was completed.
Experts do what experts do:
Unless weddings are a particularly interesting past time for you then you probably lacked experience in certain areas or may not have had the resources to do all the work internally. For those areas you might have hired an expert. Experts could include professional wedding planners, musicians, tent and table erectors, chefs, photographer, and florist. These people do not always work well together so the coordination was key. For instance if the photographer arrived to do his work before the tent erectors or the florist you could have a real problem on your hands and face embarrassment, lost time and money. That is where the detailed schedule has to be defined and followed.
Planning and then Scheduling:
With all the additional labor needed and all of the task that must be completed in a timely manner you more than likely first built a simple plan and then with time expanded on that plan with detailed steps or task for completion. That plan included pre-work items that had to be done in advance and items that would be executed on the day of the event. The plans included all the important details like what songs to play and what foods to serve. All of these could then be sequenced into the schedule and a critical path review could be performed. Normally here in the US people are not prepared to attend a wedding where it takes two days to complete the ceremony because some forgot to tell the caterer that it was a mid day wedding. Getting all of the activities completed in a 4-6 hour period is important. The critical path tells us if that is possible with the choices we have made. So both time and money become limiting factors that must be attended to. Since we know time lets look at money.
Request for Quote (RFQ) budget refinement:
If you are like me, once you decided on the date, time, and the location and the types of expert that you needed you began to get bids and and built a more complex budget with allocations to each part of the event. There were trade offs and discussions until you finalized the monetary side of the plan. Do you spend more on the dress and less on the flowers? Can we get a DJ instead of an orchestra?
At the two week out point you review the job plans, evaluate weather and family risk and put mitigation strategies into effect as required. Aunt Suzy did not want to set next to uncle Carl so you updated the seating plan one last time. You verify completion of the pre-work and you mentally prepare for the big day by meeting with your operations partner. At this point you cross the final gate and green light the event knowing that it is the best that it can be. 
Your outage should be no different. Everything you see above should be done in the plant too.
Remember all this planning went into one 4-6 hour day and your outage may be a week or even longer. Are you planning and scheduling like a wedding planner or do your weddings aimlessly go on for days?

Tuesday, July 23, 2013

Maintenance Planners: Are they focused on the future or pulled into the present? Their boss decides!

How does organizational structure dictate focus?
This week I am working with a client that is building their future state organizational structure to support reliability improvement. The question they ask was should the planners report to the maintenance supervisors for the area they plan for? My response was a sometimes controversial one but I truly believe it based on my experience and observations. Planners should not report to maintenance supervisors. They really should be peers in the organizations working as a team. If you set the organization up with planners subordinate to the maintenance supervisor then you are in essence having your future focused planner reporting to your present focused supervisor. By future focused I mean the planner should be building job plans for the future work that will be scheduled at least one week out. Your supervisor is using the plans and schedules to execute the day to day work in the present. If you create this reporting structure and if you believe the old adage “What is important to my boss is important to me” then the planner will be forced to continuously focus on the day to day issues that are important to his or her boss at the expense of the future planned and scheduled work that drives reliability improvement.  They will become a "gofer" for the supervisor and go for this part or go for that tool. This is not planning this is reacting. As you build your organizational structure you have to force proactive thinking and create barriers for some parts of the organization to keep them away from the reactive day to day activities.
What are your thoughts? Who do your planners report to? Are they focused on the proactive future or pulled into the reactive present?

Thursday, May 16, 2013

Check the Pump: Same Step Different Results

Many of us have preventive maintenance task in our facilities that are made up of a noun, a verb and a few connector words. They look like these:
  • Check the pump
  • Check the valve
  • Inspect the belts
  • Clean and inspect
Do these look familiar? If they do then ask yourself  two questions. If you send your 20 year veteran mechanic and your 4 year technician out to do these task will you get the same results? And secondly, if you send your 10 year technician out twice over  a 3 year period will he or she do the same thing both times? The answer is probably not. This introduces variability into your equipment maintenance strategy and unreliability into your assets. So what can we do? Here is one examples of how we could very simply step up repeatability and effectiveness of your tasks.
Let's say you have a PM task that traditionally would have said "Inspect Hydraulic Hoses for Wear" You could get any number of different responses and levels of performance. Even if you add the levels of wear A through D you still leave room for interpretation. Whats the difference between mild and moderate? But if we add the descriptions in parenthesis then it removes quite a bit of the ambiguity. This become a much more effective and repeatable PM step. We can take it a step further if we are equipped to collect additional data. If you record instances of each on the asset you can improve the task even more to a quantitative level. This quantitative PM is the best indicator of asset health.
The key here is that PM task do not have to be long and full of loads of pictures to provide good results you just have to choose your words wisely.

Tuesday, April 9, 2013

Tips for Your Scheduling Process Via Video

Today I thought I would share with you a video post on maintnenance scheduling with a few tips for taking your planned jobs and generating the most effective schedule.

Wednesday, March 13, 2013

Confucius say: Planning and Scheduling Cause Confusion


The topic of planning and scheduling and what each one means has been a big discussion point here in China this week. The Chinese appear to have only one word that means both planning and scheduling but in reality everywhere I teach from Europe to the Middle East and all across the Americas there is confusion  on the difference so today I thought I would share planning and then scheduling as the topic of the week.



Planning is the creation of the work package including:
Job plan and steps and durations
Parts required
Special tools required
Permits required
Personal protective equipment required
Crafts or personnel types required
Etc.

Scheduling is assigning the jobs to a time slot on a schedule.

The reason that this is important is that many of us measure percentage planned work for bench marking purposes and in more cases than not this number is actual the percent poorly scheduled because when you dive in you find that the jobs do not contain the planning elements mentioned above.
Many sites pursue ninety percent planned and scheduled work as a bench mark but you have only reached that number if you have at least the basic elements of a job plan for each job.
One example that I see often would be a work order that says only "remove and replace hot oil pump Time required 8 hours" this is not a plan at best it is a work request that has been scheduled without planning. It does not break down the task or suggest what parts will be needed or what permits might be required. While some might argue that all work is planned and that it is just the level of planning that is in questions I think you can see that it does not meet the intent of the metric and does not provide for the results we are trying to achieve. 


Thursday, February 28, 2013

The 4's and the 8's: Estimating Work Orders Wrong

This week I have been teaching asset management principles and as a part of that we were discussing the work execution process including planning of maintenance work and the schedule that follows. I shared with the group that my experience tells me than many if not most work orders are slotted into half and whole shift time estimates for the schedule. A gentleman from a very large facility chimed in and added some data to the mix. He said within his facility currently 88 percent of the work orders in his backlog were estimated at 8 hours. 6 percent were 4 hours and the remainder were at random intervals.They were half and whole shift...
If you can only achieve that level of accuracy then are the jobs really planned?
The planning process should include breaking down the job into smaller steps where estimation is easier and more accurate. If you are not breaking that job down into the component task then your inherently inaccurate job plans will lead to inaccurate schedules and that will provide for wasted craft time, excessive downtime, and broken delivery promises to operations. Job plans in general do not have to be planned to the minute but 4 hour and 8 hour is definitely not enough.  
What level of planning accuracy would you suggest works for your facility?
to the hour? to the quarter hour? 

Friday, May 11, 2012

Question from the Field: Maintenance Ready Backlog

So what is maintenance ready backlog, and why do I need 2-4 weeks of it?
Maintenance ready backlog represents the work orders that have progressed through your maintenance business process to the point that they have been approved and are planned for execution. These jobs have all of the parts, tools, and work procedures packaged and completely ready.  When we say you need two to four weeks that means that you should have enough work in this stage so that if your crafts had no break-ins or emergencies to do then you could keep them all fully employed for two to four weeks.
You need this amount for a few reasons:
First you want to be able to use these "ready to work" jobs to build your schedule each week. You need at least two weeks selection for operations and maintenance to choose from to be able to create a fully planned schedule that takes into account available equipment downtime and manpower. Your goal is to keep unplanned jobs and jobs without the parts on hand off of the schedule. By doing this you will lower maintenance cost and minimize schedule breaks. If you get below the two week mark you will start to see that you just do not have enough work orders to adequately utilize all of your crafts or the available scheduled downtime and many site are then tempted to pull in unplanned jobs and try to rush the parts and the planning.
Second, You don't need to exceed four weeks because you do not want to have excess inventory and tools tied up in the ready backlog.
To manage this level there needs to be constant communication between the Maintenance Manager, who controls the amount of craft hour available for work completion, and the Planner/Scheduler. If the Maintenance Manager were to approve extra hours of overtime for a few weeks then that will consume the ready backlog at an accelerated pace. The planner would then have to step up the production of job packages or face the possibility that they could run out of ready backlog and have to work on unplanned work.
If you can maintain the level in the band you will find that it allows for a much more effective and effective overall maintenance process. This equals lower maintenance cost for the same or higher levels of reliability.

Thursday, May 3, 2012

Questions from the Field: Wrench Time Studies

Questions: You had mentioned that we should only conduct a wrench time study on planned work.  What is the reasoning behind this?  If they get pulled off of their scheduled job to work on a“sponsored” job, should we terminate the study for that day?  It seems that we have a lot of sponsored work this week and it is somewhat difficult to stay focused on planed/scheduled work.

Answer: That is correct, planned jobs only.

The purpose of the wrench time study is to see how good the planning system is.  If they are pulled off onto sponsored work, the wrench time will likely drop significantly because troubleshooting, looking for parts, looking for prints, and waiting on production are all part of unplanned work but not a part of wrench time.

Of course this is not to say that you cannot continue the study, but it will represent something very different than if they just stayed on planned work.

So it could be as simple as this:

If they stayed on planned work then the wrench time study is a measure of the quality of the planning process.

If they do not stay on planned work, then the wrench time study is a measure the re-activeness of the organization and how well the crafts are able to accomplish unplanned work.

Both of these are valuable, but they represent two totally different things.

Hope this helps.

Andy Page
Principal
Allied Reliability Group

Wednesday, February 22, 2012

So is it a Planner, a Scheduler, or is it a Planner/Scheduler?

Recently, I had an interesting conversation about staffing the maintenance planner and scheduler roles with in a facility. The question was centered on whether a site should have the two disciplines split or if they should be combined. The answer in my mind is… it depends.
Here are my thoughts on criteria that affect the planner/scheduler organizational structure:
Size of the maintenance workforce:
If you are in a small facility it becomes very hard to support standalone schedulers. For that matter, it is hard to get one person dedicated solely to planning and scheduling. To put some numbers to it I would suggest that in an average maturity facility you will need one planner for every ten to fifteen crafts and one scheduler for every fifty crafts. The number of planners you need may drop as you mature and the job plan library is populated and refined but the scheduler will stay at a fixed level.
Reliability maturity of the facility:
More mature organizations can pool more of the crafts and share across multiple areas for maximum resource efficiency and utilization. If you share resources across multiple areas then that can be a good reason to have a standalone scheduler who devotes his time to working with all of the effected parties and creating a schedule that they can all support.
So if you consider both of these factors than it becomes a bit easier to design your organizational structure but you must keep in mind that as these size and maturity change your structure may have to change as well. 
What are your thoughts?

Monday, December 19, 2011

10 Things We Learned about Asset Health Management from Domtar


Special joint blog post with the fine folks from the Ludeca Blog:

Domtar Espanola from Ontario, Canada won Uptime Magazine’s Best Asset Health Management Program. Their goal was “Go from Reactive Maintenance to Proactive”.

To achieve this goal, they put together a plan including several proactive actions and PdM technologies integrated with an Asset Performance Management Software which allow them to closely monitor equipment health.

Kim Hunt shared some of their plan elements:
  1. Implement a precision lubrication program and oil analysis
  2. Skills training: Value your staff and empower them with training. From formal training to just watching Reliabilityweb Webinars together and afterwards eating cookies and holding discussions —great for team building!
  3. Size your equipment properly
  4. Use laser alignment and balancing for precise machine rebuilds and installs
  5. Precise operator care
  6. Maintain excellence in housekeeping
  7. Equipment health monitoring. Use predictive tools including vibration analysis to baseline your equipment.
  8. Root cause analysis and problem elimination
  9. Plan and schedule your maintenance activities with effective standard operating procedures
  10. Continuous improvement - you are never done!

What did they accomplish?
21% reduction in maintenance costs
30% increase in production efficiencies
Increased MTBF (Mean Time Between Failure)
A total average savings of US$450,000 per year without increasing actual/potential production loss.

Congratulations to Kim Hunt and her team for this award and a job well done.

Thursday, October 6, 2011

Ranting about Reliability: If It Is Not Planned Then It Is Not Scheduled!

Angry old man ranting about reliability
The ornery old man is loose on the RN blog again:

Maintenance organizations complain about getting "no respect." They moan about not being able to get time on the equipment to complete work. They set back and wonder why operations will not partner with them to improve this thing called reliability.

Well let me tell you something...You have to earn respect. Operations does not give you the equipment because you do not give it back when you promised it. You tell them it will be done in four hours and it actually takes twelve. Who wants to partner with a person who doesn't keep their promises.

You want to change this? Then start modeling the behavior that you expect from them. Demonstrate pro-activity.
Do not schedule work that has not been planned. In fact, without some level of planning, how do you even expect to be able to put a duration on it and slot it in the schedule. It can not be done with any accuracy at all.  I'm tied of seeing 4s and 8s. Real maintenance work does not come to you in half and a whole shift blocks. Nor do most maintenance folks have 8 hours of actual wrench time in a day. Lets be real here. You have to at least break the job down into some simple task that are easier to estimate. This will give you a better chance of producing an accurate schedule and building some trust. If you want to learn more about that process check out this blog or this workshop.

The point is, start cleaning up your house before you call out the neighbors in operations. Who knows maybe the neighbors will see the work you are doing and and make a change on their own.
Now get off the internet and make some reliability happen!

Monday, October 3, 2011

Is Your Work Planned or Scheduled... or Neither?

As I  have traveled from site to site and country to county and there are two words that seems to be universally confusing in the maintenance community no matter what language or culture you are a part of. Those words are planned and scheduled. In more than a few "less than best practice" sites I have ask what their percentage planned work was and have heard answers like 90 or 95% then as you ask follow up questions like "How many planners do you have?" you discover that what they really meant was that they schedule 90%. These two words get blended together and as you start to bench mark your site the definitions become both important and telling. So lets clarify these two terms a bit.

I always like to go to Merriam-Webster first and see what they have to say on the matter. They provided the following tidbit of knowledge: 

Definition of PLAN 

transitive verb

1: to arrange the parts of : design <plan a new layout>
2: to devise or project the realization or achievement of <planned their escape>
3: to have in mind : intend <plans to leave soon>
 
intransitive verb
1: to make plans <plan ahead>
2: to have a specified intention —used with on <plans on going>

This tidbit did not really clear up the matter for me so I then reached out to the Society for Maintenance and Reliability Professionals (SMRP) for the definition in their metrics compendium. In the glossary I found the following: "Planned work is work that has gone through a formal planning process to identify labor, materials, tools, and safety requirements."
Perfect! Now let's understand this word schedule. We will go back to Merriam-Webster for the definition:

Definition of SCHEDULE

transitive verb
1: to appoint, assign, or designate for a fixed time
2 a : to place in a schedule b : to make a schedule of

Now I believe we have all we need to wrap this up.
So if you are talking about planned work, percentage planned work, planned job count or most any other maintenance metric with plan in the title then we are focusing on driving the completion of job packages which contain labor required, parts needed, tools needed and any permits, forms, drawings, or documentation.
If we see the metric "percent scheduled work" or any others that may have scheduled in the title then we are talking about time and how well we were able to stay on the time line for the week's work. 
Later this week I will talk about the relationship between these two words in the maintenance and reliability world. 



Monday, August 15, 2011

The Basics of Reliability Series: Work Execution


This post is the first in a five part series that will include single point lessons that can be used to further communicate each of the topics to your organization. 

Work execution management is the full process that has to occur from the time a problem is first discovered until it is planned, scheduled, and repaired, failure history is collected, and the work order is closed or completed. This process is the backbone of reliability improvement; without it, it is very hard to see results in most of the other areas. For example, if you implement predictive tools without a good work process, all you get is a lot of identified work with no way of having it completed efficiently and effectively.

 Work Execution Management Single Point Lesson Figure 1

We will use the WE single point lesson (see figure 1), which includes the funnel model for planning and scheduling and the as is and to be reengineered model, to help individuals understand the following key points.
Forecasting work is not easy, but it is a required part of a successful work process.
Work approval processes are important for control of maintenance spending and to ensure best resource utilization.
Ready and Total Backlog concepts help maintenance managers to control staffing decisions with science instead of emotion. Planners and managers must be communicating constantly in order to properly provide for the Ready Backlog.
The funnel model also shows us where in the process we will develop effective work procedures and how we ensure that particular process has the correct inputs.
The WE single point lesson illustrates what the schedule output looks like and what inputs must be provided, including details from both operations and maintenance inputs of resources, downtime, and priority.
Last but not least, it drives the need for the process to ensure nothing is left out or missed. This process reengineering is shown as a big wasteful “as is” block that is refined into the more concise and direct “to be” block. Metrics are used to drive this change and ensure the return on investment.
We get all of this from two simple graphics that you can draw and share in a matter of minutes. 

Monday, May 23, 2011

Never Met a Maintenance Manager that had Enough People

Of all the sites I have been in all over the world, I have never met a maintenance manager who said to me “You know Shon I just have too many people.” In fact most ask me how they should go about bringing more into their fiefdom. It usually sounds a bit like this: “I need to hire planners, supervisors and a few more crafts in order to improve my reliability. If I could get support for more I could make this happen.”
Interestingly, the data tells me something entirely different. The average facility in our database is spending forty percent too much on maintenance. A portion somewhere between forty and sixty percent, depending on the industry, of that overage is labor. They are maintaining a wrench time, craft time doing value added work, of twenty three percent against a best practice of sixty-five percent. Think about that number a second, if you have twenty five craftsmen at twenty three percent wrench time that yields five point seven five FTEs (Dedicated fully utilized resource). On the flip side if you take one of those craftsmen and provide him the tools and training required to be a quality planner and scheduler then you can improve your wrench time to a very sustainable fifty-five percent. Now even with one person out of the craft ranks you can yield ten point four five FTEs without an overall head count increase. That is a eighty-one percent productivity increase… Image what that would do to your work backlog…and this is only one step to attaching high maintenance cost and unreliability. We could also talk about preventive maintenance optimization as well as others steps to provide additional gains. I'm a visual guy so here is another look at the math.
Now we know that it takes time to make the transition to the higher level of performance and that not every site is truly overstaffed but if you don’t think long and hard about wrench time productivity before you think about increasing your staff you could be doing both you, your company, and the person you hire a disservice. If you trust the benefits of planning and scheduling, the capability of your staff and you take the time to build a plan to get there you can do actually do more with less.

Monday, April 25, 2011

Pretty Pants Planners

I don’t know about you guys but I sometimes find myself on a soapbox about certain topics and recently this has been one that I keep running into and I keep finding myself up on the box.

How many of you have the dreaded triple “P”? “Pretty Pants Planner” You find them in maintenance organizations of all size and industries. They tend to be the opposite of the “gofer” planner which you may also know of. The “gofer” planner is a planner normally told to go “fer” this and go “fer” that. This planner does not have a clear future focus and is typically just running parts, information, and tools in a reactive manner for the maintenance supervisor and to the craftsmen. On the other hand the “Pretty Pants Planner” lives in a world where they hardly ever even see the plant floor. In the wild, you will recognize these planners by their clothing and the tendency to cohabitate. Typically they shun the standard plant attire and wear nice pants and designer shirts, sometimes in even white. These pants have never seen the soils of manufacturing or the sweat of the production process. Now please don’t misunderstand my rant, I do not believe that planners should be on the floor all the time after all the planners primary function is to create job plans. The amount of floor time should and will vary with the maturity of the organization. (See Figure 1 below) The red in the first continuum represents the immature planning organization as more of the elements are are put in place then the organization moves to green. This is tied to the second continuum that shows "gofer" to triple P. Notice a mature organization does not reach the extreme triple P end of the scale.
   
Figure 1 The Continuum for Planning Maturity
 Click the graphic to enlarge
To speak in extremes, if your site has limited or nonexistent planning maturity characterized as: no Job Plan Library, limited accurate Bill of Materials, no Preventive Maintenance (PM) task, no predictive maintenance (PdM) program, lack luster Computerized Maintenance Management (CMMS or EAM), underutilized business processes, then your site will need more planners (ratio of 8:1) and the planners will need to spend more time on the floor. If you are in this situation then you will need to fight harder to keep the planners from getting sucked into the day to day work that is the world of the supervisor.
To move to the other extreme as shown on the chart in figure 1, if you have a very mature organization your planners will spend much less time on the floor (and there will be less of them per craftsman 30:1) but they still should be out there 10% of their work week.
This time on the floor is used to review the plans and insure that nothing has changed or has been missed. For example how many times have you seen craftsmen arrive to the site of a planned job and realize:
a. that they do not have a special tool that is required
b. a pipe is in the way of completing the plan as is
c. a guard has been added and not considered in the plan and the time estimate that was put forth.
Many of these situations can be eliminated with a walk through with the planned job in hand prior to the week of execution.
The key for these facilities is striking the balance based on their maturity.

So I leave you with these questions:
How mature is your organization?
Where on the scale are your planners?
Is there a match?